# The Net Zero Teesside Order 2024, Paragraph 232: Co-operation

Extent: E+W+S

Insofar as the Anglo American Specified Works are or may be undertaken concurrently with the Specified Works within the Shared Area, the undertaker must—
(a) co-operate with Anglo American with a view to ensuring—
(i) the co-ordination of programming of all activities and the carrying out of works within the Shared Area; and
(ii) that access for the purposes of the construction and operation of the Woodsmith Project is maintained for Anglo American and its ... employees, contractors and sub-contractors; and
(b) use reasonable endeavours to avoid any conflict arising from the carrying out of the Respective Projects.

---