  "url": "https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-236",
  "json_url": "https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-236.json",
  "legislation": "uksi/2024/174",
  "legislation_title": "The Net Zero Teesside Order 2024",
  "legislation_url": "https://openlegislation.uk/net-zero-teesside-order-2024",
  "path": "schedule/12/paragraph/236",
  "kind": "paragraph",
  "number": "236",
  "heading": "Interface Design Process",
  "text": "(1) Prior to the seeking of any consent under this Part of this Schedule, the undertaker must, unless Anglo American has brought forward works in that part of the Shared Area before the undertaker, participate in a design and constructability review for that part of the Shared Area which shall, at a minimum (unless otherwise agreed), include the following matters—\n(a) a Front End Engineering Design (FEED) level indicative construction work-pack;\n(b) a hazard and operability study;\n(c) a construction hazard study; and\n(d) in respect of any part of the Shared Area which is to accommodate the overland conveyor, information to demonstrate that the relevant Specified Works account for the interface with any overland conveyor located in that part of the Shared Area.\n(2) Unless otherwise agreed, the undertaker must submit the outcome of the design and constructability review referred to in sub-paragraph (1) to Anglo American for approval prior to the seeking of any consent under this Part of this Schedule.\n(3) The undertaker must at all times design and construct the Specified Works in compliance with the relevant approved design and constructability review pursuant to sub-paragraph (2).\n(4) The undertaker may undertake a single design and constructability review process for one or more parts of the Shared Area and any approved design and constructability review may be amended if agreed by Anglo American.\n(5) In considering any request for consent or approval under this Part of this Schedule, Anglo American must not refuse consent for details that are consistent with those approved under sub-paragraph (2) unless Anglo American reasonably believes that the relevant agreed design and constructability review is materially out of date or is inapplicable due to a change in either the authorised development or the Woodsmith Project.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 236 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/236",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}