{
  "url": "https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-245",
  "json_url": "https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-245.json",
  "legislation": "uksi/2024/174",
  "legislation_title": "The Net Zero Teesside Order 2024",
  "legislation_url": "https://openlegislation.uk/net-zero-teesside-order-2024",
  "path": "schedule/12/paragraph/245",
  "kind": "paragraph",
  "number": "245",
  "heading": "Dispute Resolution",
  "text": "The expert must consider where relevant—\n(a) the development outcomes sought by the undertaker and Anglo American;\n(b) the ability of the undertaker and Anglo American to achieve the outcomes referred to sub-paragraph (a) in a timely and cost-effective manner;\n(c) any increased costs on any Party as a result of the matter in dispute;\n(d) whether under this Order or the York Potash Order, the undertaker’s or Anglo American’s outcomes could be achieved in any alternative manner without the Specified Works being materially compromised in terms of increased cost or increased length of programme; and\n(e) any other important and relevant considerations.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 245 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/245",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}