# The Net Zero Teesside Order 2024, Paragraph 259: Consent for works

Extent: E+W+S

Before commencing the construction of any part of the authorised development including any permitted preliminary works within the Teesworks site, the undertaker must first submit to the Teesworks entity for its approval the works details for the work and such further particulars as the Teesworks entity may, within 30 days from the day on which the works details are submitted under this paragraph, reasonably require.

---