  "heading": "Provision for diversion works",
  "text": "If a diversion notice is issued to the undertaker before the expiry of the period under paragraph 270, the undertaker must notify the Teesworks entity no later than 30 days after the date of receipt of the diversion notice confirming whether the undertaker—\n(a) agrees to diversion work;\n(b) does not agree to the diversion work; or\n(c) requires additional information to consider whether it agrees to the diversion work (an “information notice”).",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 273 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/273",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}