# The Net Zero Teesside Order 2024, Paragraph 276: Provision for diversion works

Extent: E+W+S

Where the undertaker notifies the Teesworks entity under paragraph 272(b) that it does not agree to a diversion work, that notice must set out the reasons why the undertaker does not agree that the diversion work satisfies the diversion condition along with an indication of what would be required to make it satisfy the diversion condition.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/276 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-276
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.