# The Net Zero Teesside Order 2024, Paragraph 282: Provision for diversion works

Extent: E+W+S

If a reference is made to arbitration under paragraph 285 the arbitrator must determine whether the terms of the diversion works agreement can reasonably be in accordance with the diversion condition and if it can then the arbitrator must determine the terms of the diversion works agreement and which must be in accordance with the diversion condition.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/282 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-282
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.