# The Net Zero Teesside Order 2024, Paragraph 291: Consent under this Part

Extent: E+W+S

Before commencing any part of the authorised development which would have an effect on the operation or maintenance of or access to the Breagh Pipeline or the Breagh Pipeline Operations, the undertaker must submit to the Breagh Pipeline Owners the works details for the proposed works and such further particulars as the Breagh Pipeline Owners may, within 28 days from the day on which the works details are submitted under this paragraph, reasonably require.

---