# The Net Zero Teesside Order 2024, Paragraph 309: Authorisation of works details affecting pipelines or protected crossing

Extent: E+W+S

(1) Before commencing any part of a relevant work the undertaker must submit to HPU the works details in respect of any affected asset and obtain a written acknowledgement of receipt of those works details from the specified persons in relation to the affected asset concerned.
(2) The undertaker must as soon as reasonably practicable provide such further particulars as HPU may, within 30 days (or such longer period as is agreed between the parties) from the receipt of the works details under sub-paragraph (1), reasonably require.

---