# The Net Zero Teesside Order 2024, Paragraph 313: Notice of works

Extent: E+W+S

The undertaker must provide to HPU a minimum of 28 days’ notice prior to commencing any relevant work in order that an engineer can be made available to observe the relevant works and, when required, advise on the necessary safety precautions.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/313 (the official version)