  "heading": "Further provisions about works",
  "text": "(1) All piling within 1.5 metres of the centreline of a pipeline must be non-percussive.\n(2) Where piling is required within 50 metres of the centreline of a pipeline or which could have an effect on the operation or maintenance of a pipeline or access to a pipeline, details of the proposed method for and location of the piling must be provided to HPU for approval in accordance with paragraph 308.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 315 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/315",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}