# The Net Zero Teesside Order 2024, Paragraph 334: Consent under this Part

Extent: E+W+S

Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the Navigator Terminals operations or all necessary and existing access to them, the undertaker must submit to Navigator Terminals the works details for the proposed works and such further particulars as Navigator Terminals may, within 28 days from the day on which the works details are submitted under this paragraph, reasonably require for approval by Navigator Terminals.

---