# The Net Zero Teesside Order 2024, Paragraph 337


(1) The authorised development must be carried out with good and suitable materials in a good and workmanlike manner in accordance with the works details approved under paragraph 334 and any requirements imposed on the approval under paragraph 335 and all other statutory and other requirements or regulations.
(2) Where there has been a reference to an arbitrator in accordance with paragraph 339 and the arbitrator gives approval for the works details, the authorised development must be carried out in accordance with the approval and conditions contained in the decision of the arbitrator under paragraph 339.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/337 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-337