(1) Where in consequence of the proposed construction of any of the authorised development, the undertaker or NW requires the removal of apparatus or NW makes requirements for the protection or alteration of apparatus, the undertaker must use all reasonable endeavours to co-ordinate the execution of the works in the interests of safety and the efficient and economic execution of the authorised development and taking into account the need to ensure the safe and efficient operation of NW’s undertaking and NW must use all reasonable endeavours to co-operate with the undertaker for that purpose.
(2) Where the undertaker identifies any apparatus which may belong to or be maintainable by NW but which does not appear on any statutory map kept for the purpose by NW, it shall inform NW of the existence and location of the apparatus as soon as reasonably practicable.
(3) Nothing in this Part of this Schedule affects the provisions of any enactment or agreement regulating the relations between the undertaker and NW in respect of any apparatus laid or erected in land belonging to the undertaker on the date on which this Order is made.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/350 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-350
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.