  "text": "(1) Before commencing any part of the authorised development which would have an effect on the operations or access to any land owned by NTL, NTR or NTLL which is adjacent to the Order limits, the undertaker must submit to the NT Group the works details for the proposed works and such further particulars as the NT Group may, within 28 days from the day on which the works details are submitted under this paragraph, reasonably require.\n(2) No works comprising any part of the authorised development which would have an effect on the operations or access to any land owned by NTL, NTR or NTLL which is adjacent to the Order limits are to be commenced until the works details in respect of those works submitted under sub-paragraph (1) have been approved by the NT Group.\n(3) Any approval of the NT Group under sub-paragraph (2) must be given in respect of NTL, NTR and NTLL together, must not be unreasonably withheld or delayed but may be given subject to such reasonable requirements as the NT Group may require to be made for them to have reasonable access with or without vehicles to the operations and any land owned by NTL, NTR or NTLL which is adjacent to the Order limits.\n(4) The authorised development must be carried out in accordance with the works details approved under sub-paragraph (2) and any requirements imposed on the approval under sub-paragraph (3).\n(5) Where there has been a reference to an arbitrator in accordance with article 47 (arbitration) and the arbitrator gives approval for the works details, the authorised development must be carried out in accordance with the approval and conditions contained in the decision of the arbitrator under article 47.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 370 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/370",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",