  "url": "https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-376",
  "json_url": "https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-376.json",
  "legislation": "uksi/2024/174",
  "legislation_title": "The Net Zero Teesside Order 2024",
  "legislation_url": "https://openlegislation.uk/net-zero-teesside-order-2024",
  "path": "schedule/12/paragraph/376",
  "kind": "paragraph",
  "number": "376",
  "heading": null,
  "text": "No relevant works are to be commenced until the design package has been developed and submitted by the undertaker and approved or deemed approved by the NSMP entity in accordance with the design approval process at paragraphs 377 to 382 below.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 12 para. 376 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/376",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}