# The Net Zero Teesside Order 2024, Paragraph 396: Approval Principles: Relevant Works Package B

Extent: E+W+S

The undertaker and the NSMP entity must, in carrying out their obligations in relation to the approval of the design package for relevant works package B—
(a) co-operate with each other with a view to ensuring—
(i) the compatibility of the authorised development and the NSMP operations; and
(ii) the co-ordination of the construction programming of the authorised development and the NSMP operations; and
(b) use reasonable endeavours to avoid any conflict arising from the carrying out of the authorised development and the NSMP operations, having regard always to the approval principles in paragraph 395.

---