# The Net Zero Teesside Order 2024, Paragraph 92: Cathodic protection testing

Extent: E+W+S

Where in the reasonable opinion of Exolum or the undertaker—
(a) the authorised development might interfere with the cathodic protection forming part of the Exolum operations; or
(b) the Exolum operations might interfere with the proposed or existing cathodic protection forming part of the authorised development,
Exolum and the undertaker must co-operate in undertaking the tests which they consider reasonably necessary for ascertaining the nature and extent of such interference and implement measures for providing or preserving cathodic protection.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/92 (the official version)