# The Net Zero Teesside Order 2024, Paragraph 98: Consent under this Part

Extent: E+W+S

Before commencing any part of the authorised development which would have an effect on the operation or maintenance of the INEOS operations or access to them or which would otherwise be located on land within the INEOS operations, the undertaker must submit to INEOS the works details for the proposed works and such further particulars as INEOS may, within 28 days from the day on which the works details are submitted under this paragraph, reasonably require.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/98 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-98
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.