# The Net Zero Teesside Order 2024, Paragraph 99: Consent under this Part

Extent: E+W+S

No works comprising any part of the authorised development which would have an effect on the operation or maintenance of the INEOS operations or access to them or which would otherwise be located on land within the INEOS operations are to be commenced until the works details in respect of those works submitted under paragraph 98 have been approved by INEOS.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/99 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-99
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.