# The Net Zero Teesside Order 2024, Paragraph 390

Extent: E+W+S

Any approval of the NSMP entity required under Part A or Part B of this Part of this Schedule must not (subject to paragraphs 390 and 391 below) be unreasonably withheld or delayed but may be given subject to the NSMP requirements (with respect to relevant works package A) and in considering any request to agree or approve details under Part A or B the NSMP Entity must make its decision in accordance ...—
(a) with respect to relevant works package A, the approval principles set out at paragraphs 390 to 394 of this Part; and
(b) with respect to relevant works package B, with the approval principles set out at paragraphs 395 and 396 of this Part.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/12/paragraph/wrapper1/390 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-12/paragraph-wrapper1/390
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.