# The Net Zero Teesside Order 2024, Paragraph 16: Construction environmental management plan

Extent: E+W+S

(1) No part of the authorised development may commence, save for the permitted preliminary works, until a construction environmental management plan for that part has been submitted to and, after consultation with the Environment Agency, Sembcorp and STDC, approved by the relevant planning authority.
(2) The plan submitted and approved must be in accordance with the framework construction environmental management plan and the indicative landscape and biodiversity strategy and incorporate—
(a) a code of construction practice, specifying measures designed to minimise the impacts of construction works;
(b) a scheme for the control of any emissions to air;
(c) a soil management plan;
(d) a sediment control plan;
(e) a scheme for environmental monitoring and reporting during the construction of the authorised development, including measures for undertaking any corrective actions;
(f) a scheme for the notification of any significant construction impacts on local residents and businesses for handling any complaints received relating to such impacts during the construction of the authorised development;
(g) surface and foul water drainage measures that are in accordance with the surface and foul water drainage scheme submitted under requirement 11(1);
(h) the measures outlined in paragraphs 15.7.4, 15.8.12 to 15.8.16, 15.8.19 and 15.9.1 in Appendix B: Ornithology in the Environmental Statement Addendum – Volume I of the ES addendum or such other measures to achieve the same maximum noise levels as are set out in paragraphs 15.8.13 to 15.8.16 of Appendix B: Ornithology in the Environmental Statement Addendum – Volume I of the ES addendum;
(i) a groundwater monitoring plan that comprises monitoring of groundwater levels and chemical contaminants of concern to inform the construction design process and which must take into account the updated hydrogeological impact assessment and any further ground investigation reports and groundwater monitoring required by requirement 13(2)(f);
(j) a materials management plan in accordance with paragraph 5.3.76 of Chapter 5 of the environmental statement;
(k) a hazardous materials management plan in accordance with paragraph 10.5.3 in Chapter 10 of the environmental statement; and
(l) any other management or mitigation plans set out in the framework construction environmental management plan.
(3) All construction works associated with the authorised development must be carried out in accordance with the relevant approved construction environmental management plan unless otherwise agreed with the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/2/paragraph/16 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-2/paragraph-16/enacted