# The Net Zero Teesside Order 2024, Paragraph 27: Aviation warning lighting

Extent: E+W+S

(1) No part of the authorised development comprised within Work No. 1 or 7 may commence, save for the permitted preliminary works, until details of the aviation warning lighting to be installed for that part during construction and operation have been submitted to, and after consultation with the Civil Aviation Authority, approved by the relevant planning authority.
(2) The aviation warning lighting approved pursuant to sub-paragraph (1) must be installed and operated in accordance with the approved details.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/2/paragraph/27 (the official version)
Page: https://openlegislation.uk/net-zero-teesside-order-2024/schedule-2/paragraph-27/enacted
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.