# The Net Zero Teesside Order 2024, Paragraph 28: Air safety

Extent: E+W+S

No part of Work Nos. 1 or 7 may commence, save for the permitted preliminary works, until details of the information that is required by the Defence Geographic Centre of the Ministry of Defence to chart the site for aviation purposes for that part have been submitted to and approved by the relevant planning authority.

---
Source: https://www.legislation.gov.uk/uksi/2024/174/schedule/2/paragraph/28 (the official version)