  "heading": "Detailed design",
  "text": "(1) No part of the authorised development comprised in Work No. 1 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and approved by the relevant planning authority (following consultation with STDC)—\n(a) the siting, layout, scale and external appearance, including the colour, materials and surface finishes of all new permanent buildings and structures;\n(b) finished floor levels;\n(c) the height of the stacks which must be at a level at which the environmental effects will be no worse than those identified in Chapter 8 of the environmental statement;\n(d) hard standings; and\n(e) the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities, cycle parking and routes, and pedestrian routes.\n(2) No part of the authorised development comprised in Work No. 2A may commence, save for the permitted preliminary works, until details of the following, to the extent that they are above mean low water springs, for that part have been submitted to and approved by the relevant planning authority (following consultation with Sembcorp, STDC and the TG entities)—\n(a) the route and method of installation of the high-pressure gas supply pipeline and any electrical supply, telemetry and other apparatus;\n(b) the number and location of cathodic protection posts and marker posts;\n(c) surface water drainage; and\n(d) works involving trenchless technologies including their location.\n(3) No part of the authorised development comprised in Work No. 2B may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and approved by the relevant planning authority (following consultation with Sembcorp, STDC and the TG entities)—\n(a) the siting, layout, scale and external appearance, including the colour, materials and surface finishes of all new permanent buildings, structures and above ground apparatus;\n(b) hard standings;\n(c) the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities; and\n(d) works involving trenchless technologies including their location.\n(4) No part of the authorised development comprised in Work No. 3 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and approved by the relevant planning authority (following consultation with Sembcorp and STDC)—\n(a) the route and method of installation of the 275 kilovolt electrical cables and control system cables running from Work No. 1 to the existing substation at Tod Point;\n(b) the connections within the existing substation at Tod Point, including electrical cables, connections to the existing busbars and new, upgraded or replacement equipment; ...\n(c) works involving trenchless technologies including their location ; and\n(d) the siting and external appearance of cable support structures.\n(5) No part of the authorised development comprised in Work No. 4 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and approved by the relevant planning authority (following consultation with STDC)—\n(a) route and method of construction of the water supply pipelines; and\n(b) works involving trenchless technologies including their location.\n(6) No part of the authorised development comprised in Work No. 5 may commence, save for permitted preliminary works, until details of the following for that part have been submitted to and approved by the relevant planning authority (following consultation with Sembcorp and STDC)—\n(a) the route and method of construction of any new wastewater water pipelines above mean low water springs; and\n(b) works involving trenchless technologies including their location.\n(7) No part of the authorised development comprised in Work No. 6 may commence, save for the permitted preliminary works, until details of the following, to the extent that they are above mean low water springs, for that part have been submitted to and approved by the relevant planning authority (following consultation with Sembcorp and STDC)—\n(a) the route and method of installation of the carbon dioxide gathering network pipelines and any electrical supply, telemetry and other apparatus;\n(b) the number and location of cathodic protection posts and marker posts; and\n(c) works involving trenchless technologies including their location.\n(8) No part of the authorised development comprised in Work No. 7 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and approved by the relevant planning authority (following consultation with STDC)—\n(a) the siting, layout, scale and external appearance, including the colour, materials and surface finishes of all new permanent buildings and structures;\n(b) finished floor levels;\n(c) hard standings; and\n(d) the internal vehicular access and circulation roads, loading and unloading, vehicle parking and turning facilities, and pedestrian routes.\n(9) No part of the authorised development comprised in Work No. 8 may commence, save for the permitted preliminary works, until details of the following for that part have been submitted to and approved by the relevant planning authority (following consultation with STDC)—\n(a) the route and method of installation of the carbon dioxide export pipeline and any electrical supply, telemetry and other apparatus;\n(b) the number and location of cathodic protection posts and marker posts; and\n(c) works involving trenchless technologies including their location.\n(10) No part of the authorised development comprised in Work No. 9 may commence until details of the following for that part have been submitted to and approved by the relevant planning authority (following consultation with Sembcorp and STDC)—\n(a) layout and heights of contractor compounds and construction staff welfare facilities; and\n(b) vehicle access, parking and cycle storage facilities.\n(11) Work Nos. 1, 3 and 7 must be carried out in accordance with the design parameters in Schedule 15.\n(12) Subject to other terms of this Order, Work Nos. 1, 2, 3, 4, 5, 6, 7, 8 and 9 must be carried out in accordance with the details approved in accordance with sub-paragraphs (1) to (10) above, unless otherwise agreed with the relevant planning authority.\n(13) The details to be submitted to and approved by the relevant planning authority under sub-paragraphs (1) and (8) must be in accordance with the principles in section 7 and 8 of the design and access statement.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "F",
      "label": "F1",
      "text": "Word in Sch. 2 para. 3(4)(b) omitted (29.10.2025) by virtue of The Net Zero Teesside (Amendment) Order 2025 (S.I. 2025/1143), arts. 1, 16(a)"
    },
    {
      "type": "F",
      "label": "F2",
      "text": "Word in Sch. 2 para. 3(4)(c) substituted for full stop (29.10.2025) by The Net Zero Teesside (Amendment) Order 2025 (S.I. 2025/1143), arts. 1, 16(b)"
    },
    {
      "type": "F",
      "label": "F3",
      "text": "Sch. 2 para. 3(4)(d) inserted (29.10.2025) by The Net Zero Teesside (Amendment) Order 2025 (S.I. 2025/1143), arts. 1, 16(c)"
    },
    {
      "type": "I",
      "label": "I1",
      "text": "Sch. 2 para. 3 in force at 11.3.2024, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2024/174/schedule/2/paragraph/3",
    "retrieved_at": "2026-10-28T21:34:40.750770+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}