# The Network Rail (Blackthorn and Piddington) (Land Acquisition) Order 2015, Schedule 2: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN


(1)
Area
(2)
Plot numbers
(3)
Purpose for which temporary possession may be taken
County of Oxfordshire
District of Cherwell
1, 4, 6, 7
Working site and access
10, 12
Environmental mitigation works
13, 17, 22
Working site, access and environmental mitigation works
25
Environmental mitigation works
26
Working site, access and environmental mitigation works
29, 31, 33
Working site and access
39, 41
Working site, access and environmental mitigation works
44, 47, 50, 53, 56, 58, 60, 62, 64
Working site and access
67
Working site, access and environmental mitigation works
68
Environmental mitigation works
County of Buckinghamshire
District of Aylesbury Vale
69
Environmental mitigation works
70
Working site, access and environmental mitigation works
73, 74
Working site and access
77, 79, 80, 83, 84
Working site and access

---
Source: https://www.legislation.gov.uk/uksi/2015/1684/schedule/2 (the official version)
Page: https://openlegislation.uk/network-rail-blackthorn-and-piddington-land-acquisition-order-2015/schedule-2
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.