# The Network Rail (Cambridge South Infrastructure Enhancements) Order 2022, Schedule 9: ACCESS TO WORKS


(1)
Area
(2)
Description of Access
In the County of Cambridgeshire, City of Cambridge
Improvement and widening of the access off Long Road marked A1 on sheet 1 of the deposited plans
Creation of new temporary vehicular access off Francis Crick Avenue marked A2 on sheet 2 the deposited plans
Creation of new vehicular access to Cambridge South station off Francis Crick Avenue marked A3 on sheet 2 the deposited plans
Widening and improvement of access off Addenbrookes Road roundabout with the National Cycle Network marked A4 on sheet 3 of the deposited plans
Widening and improvement of access off Addenbrookes Road roundabout leading to the pumping station at a point marked A5 on sheet 3 of the deposited plans
In the County of Cambridgeshire, District of South Cambridgeshire
Widening and improvement of access and visibility splay works at Granhams Road marked A6 on sheet 5 of the deposited plans
Widening and improvement of access at Addenbrookes Road marked A7 on sheet 6 of the deposited plans

---
Source: https://www.legislation.gov.uk/uksi/2022/1406/schedule/9 (the official version)
Page: https://openlegislation.uk/network-rail-cambridge-south-infrastructure-enhancements-order-2022/schedule-9
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.