# The Network Rail (Church Fenton Level Crossing Reduction) Order 2024, Schedule 4: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN


(1)
Area
(2)
Number of land shown on the deposited plan
(3)
Purpose for which temporary possession may be taken
(4)
Relevant part of the authorised works
County of North Yorkshire
016
Protection of field drainage
Work Nos.1 and 2
018
Access for construction of works
Work No.1
023
Worksite and access
Work No.3
028
Worksite and access
Work Nos.1,2, and 3
031
Worksite and access
Work No.1 and diversion of utility apparatus

---
Source: https://www.legislation.gov.uk/uksi/2024/526/schedule/4 (the official version)
Page: https://openlegislation.uk/network-rail-church-fenton-level-crossing-reduction-order-2024/schedule-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.