Explanatory note
(This note is not part of the Order)
This Order confers powers on Network Rail to stop up the Abbots Ripton level crossing and to construct works in connection with the closure of the level crossing, the extinguishment of the existing right of way and the creation of alternative public rights of way. The Order further confers powers on Network Rail for the temporary use of land in connection with the construction of the public rights of way provided to replace the crossing.
A copy of the deposited plans and the book of reference referred to in the Order may be inspected at the offices of the Company Secretary and Solicitor to Network Rail Infrastructure Limited at 1 Eversholt Street, London, NW1 2DN.