Article 22 Power to acquire land
Network Rail may acquire compulsorily—
so much of the land shown on the deposited plans as lying within the limits of deviation and described in the book of reference as may be required for the purposes of the authorised works;
so much of the land specified in columns (1) and (2) of Schedule 2 (acquisition of land for ancillary works) (being land shown on the deposited plans and described in the book of reference) as may be required for the purpose specified in relation to that land in column (3) of that Schedule; and
so much of the land shown marked 0652 on the deposited plans and described in the book of reference as may be required for the Winslow Station works,
and may use any land so acquired for those purposes, or for any other purposes that are ancillary to its railway undertaking.