# The Network Rail (Essex and Others Level Crossing Reduction) Order 2022, Paragraph 12

Extent: E+W+S

Any dispute arising between Network Rail and the drainage authority under this Schedule, if the parties agree, is to be determined by arbitration under article 37 (arbitration), but otherwise is to be determined by the Secretary of State for Environment, Food and Rural Affairs and the Secretary of State for Transport acting jointly on a reference to them by Network Rail or the drainage authority, after notice in writing by one to the other.

---
Source: https://www.legislation.gov.uk/uksi/2022/651/schedule/13/paragraph/12 (the official version)
Page: https://openlegislation.uk/network-rail-essex-and-others-level-crossing-reduction-order-2022/schedule-13/paragraph-12
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.