Schedule 1 SCHEDULED WORKS

Original text. Later amendments are not shown.

In the County of Derbyshire, Peak District National Park—

Work No. 1 – A railway embankment and associated maintenance walkway (23 metres in length) commencing at a point 370 metres east of the junction of Sickleholme with Hathersage Road (A6187) and terminating at a point 390 metres east of that junction.

Work No. 2 – A railway cutting and associated maintenance walkway (30.94 metres in length) commencing at a point 395 metres east of the junction of Sickleholme with Castleton Road (A6187) and terminating at a point 425 metres east of that junction.

Work No. 3 – A railway cutting and a railway embankment (501.38 metres in length) commencing at a point 156 metres west of culvert MAS/25A beneath the Manchester to Sheffield Railway and terminating at a point 77 metres east of culvert MAS/24 beneath the Manchester to Sheffield Railway. Work No. 3 includes extensions to culvert MAS/25A, Underbridge MAS/25, culvert MAS/24 and the construction of a maintenance walkway.

Work No. 3a – A diversion of an oil pipeline (25.72 metres in length) commencing beneath a point 59 metres north-west of culvert MAS/24 continuing south-westwards beneath Work No.3 and terminating beneath the Manchester to Sheffield Railway at a point 5 metres west of Underbridge MAS/25.

Work No. 4 – A retaining wall and the reprofiling of an existing railway embankment (49.72 metres in length), commencing at a point 52 metres west of Underbridge MAS/23 beneath the Manchester to Sheffield Railway and terminating at a point east of its commencement.

Work No. 5 – A footbridge (51.86 metres in length) over the Manchester to Sheffield Railway commencing at a point 10 metres north-east of the Hathersage West level crossing and terminating at a point 8 metres south-west of that crossing.

In the City of Sheffield—

Work No. 6 – A railway (28.90 metres in length) commencing at a point 116 metres east of the junction of Five Trees Avenue with Five Trees Drive passing north-eastwards and terminating at a point 177 metres north-west of the junction of Rosamond Avenue with Everard Avenue.

Work No. 7 – Work number not used.

Work No. 8 – A footbridge (53.08 metres in length) within Dore and Totley Station commencing at a point 58 metres south-east of the junction of Dore Road with Abbeydale Road South (A621) and terminating at a point 66 metres east of the junction of Abbeydale Road South (A621) with Ladies Spring Grove.

Work No. 9 – An extension of the existing platform at Dore and Totley Station (36.03 metres in length) commencing at a point 47 metres east of the junction of Dore Road with Abbeydale Road South (A621) and terminating at a point 57 metres north-east of that junction.

Work No. 10 – A new platform at Dore and Totley Station (153 metres in length) commencing at a point 113 metres east of the junction of Abbeydale Road South with Twentywell Lane and terminating at a point 68 metres north-east of the junction of Dore Road with Abbeydale Road South (A621).