Schedule 8 LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN
(1) Area | (2) Number of land shown on the deposited plans | (3) Purpose for which temporary possession may be taken | (4) Authorised works |
|---|---|---|---|
| County of Derbyshire, Peak District National Park | 1a | Working site and access | Work Nos. l and 2 |
| 2 | Access | Work Nos. 1 and 2 | |
| 2a and 3a | Working site and access | Work Nos. 1 and 2 | |
| 3b | Access | Work Nos. 3 and 3a | |
| 5 and 7 | Access | Work Nos. 1 and 2 | |
| 9 and 12 | Access | Work No. 3 | |
| 15 | Working site, access and environmental mitigation works | Work Nos. 3 and 3a | |
| 16, 17, 18, 21 and 22a | Access | Work Nos. 3 and 3a | |
| 23 and 24 | Working site, access and environmental mitigation works | Work Nos. 3, 3a and 4 | |
| 23b and 25 | Access | Work Nos. 3, 3a and 4 | |
| 26 | Working site and access | Work Nos. 3, 3a and 4 | |
| 27, 28b and 29a | Access | Work Nos. 3, 3a and 4 | |
| 30 | Access | Work No. 5 | |
| 31 and 36 | Working site, access, temporary footpath diversion and environmental mitigation works | Work No. 5 | |
| City of Sheffield | 38 and 40a | Access | Work No. 6 |
| 39 and 40 | Access and environmental mitigation works | Work No. 6 | |
| 39a | Working site, access and environmental mitigation works | Work No. 6 | |
| 42, 44 and 49 | Access and environmental mitigation works | Work No. 6 | |
| 43 and 45 | Environmental mitigation works | Work No. 6 | |
| 51 | Working site, access and environmental mitigation works | Work No. 6 | |
| 52 | Working site, access, temporary footpath diversion and environmental mitigation works | Work No. 6 | |
| 70, 73 and 75 | Working site and access | Work Nos. 8, 9 and 10 | |
| 76 | Access | Work Nos. 8, 9 and 10 |