  "url": "https://openlegislation.uk/network-rail-ipswich-chord-order-2012/article-35",
  "json_url": "https://openlegislation.uk/network-rail-ipswich-chord-order-2012/article-35.json",
  "legislation": "uksi/2012/2284",
  "legislation_title": "The Network Rail (Ipswich Chord) Order 2012",
  "legislation_url": "https://openlegislation.uk/network-rail-ipswich-chord-order-2012",
  "path": "article/35",
  "kind": "article",
  "number": "35",
  "heading": "Procedure in relation to approvals etc. under requirements",
  "text": "Where an application is made for any consent, agreement or approval required by a requirement under Part 2 (requirements) of Schedule 1 (authorised development and requirements), the following provisions apply, so far as they relate to a consent, agreement or approval of a local planning authority required by a condition imposed on a grant of planning permission, as if the requirement was a condition imposed on the grant of planning permission—\n(a) sections 78 and 79 of the 1990 Act (right of appeal in relation to planning decisions); and\n(b) any orders, rules or regulations which make provision in relation to appeals under section 78 of the 1990 Act.",
  "extent": "E+W+S",
  "status": null,
  "version": "current",
  "annotations": [
    {
      "type": "I",
      "label": "I1",
      "text": "Art. 35 in force at 26.9.2012, see art. 1"
    }
  ],
  "outstanding_effects": [],
  "provenance": {
    "source": "legislation.gov.uk",
    "source_url": "https://www.legislation.gov.uk/uksi/2012/2284/article/35",
    "retrieved_at": "2026-10-29T01:20:05.499375+00:00"
  },
  "licence": "Open Government Licence v3.0",
  "licence_url": "https://www.nationalarchives.gov.uk/doc/open-government-licence/version/3/",
  "attribution": "Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives."
}