No stage of the authorised development is to commence until a written landscaping scheme for that stage has been submitted to and approved by the relevant planning authority. The submitted scheme must reflect the mitigation measures set out in Chapter 8, Technical Report 8, Townscape and Visual Effect Assessment in Volume 3 of the Environmental Statement, with particular reference to paragraphs 1.6.9 to 1.6.18 of the Chapter. The landscaping scheme must include details of—
(a) location, number, species, size and planting density of any proposed planting;
(b) cultivation, importing of materials and other operations to ensure plant establishment;
(c) implementation timetables for all landscaping work;
(d) temporary fencing to protect trees adjacent to the work
(e) measures relating to the removal of rabbit protection provided for trees and shrubs and to the checking, adjusting and repairing of all stakes, ties, shelters and fencing used in accordance with the scheme; and
(f) proposals to take account of the presence of trees with trunks of a diameter of 100 millimetres or more and to minimise the loss of such trees.

---
Source: https://www.legislation.gov.uk/uksi/2012/2284/schedule/1/paragraph/4 (the official version)
Page: https://openlegislation.uk/network-rail-ipswich-chord-order-2012/schedule-1/paragraph-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.