OpenLegislation

Article 3 Access to works

Original text. Later amendments are not shown.

(1)

Network Rail may, for the purposes of the authorised works, form and lay out such other means of access or alter or improve existing means of access at such locations within the Order land as Network Rail reasonably requires for the purposes of the authorised works, as may be approved by the highway authority, but such approval must not be unreasonably withheld.

(2)

If a highway authority fails to notify Network Rail of its decision within 28 days of receiving an application for approval under paragraph (1), that highway authority is deemed to have granted approval.