# The Network Rail (Norton Bridge Area Improvements) Order 2014, Article 20: Compulsory acquisition of land

Extent: E+W+S

(1) Network Rail may acquire compulsorily so much of the Order land as is required for the authorised development or to facilitate, or is incidental to, it.
(2) This article is subject to paragraph (2) of article 22 (compulsory acquisition of rights) and paragraph (8) of article 28 (temporary use of land by Network Rail).

---
Source: https://www.legislation.gov.uk/uksi/2014/909/article/20 (the official version)
Page: https://openlegislation.uk/network-rail-norton-bridge-area-improvements-order-2014/article-20
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.