# The Network Rail (Norton Bridge Area Improvements) Order 2014, Article 9: Street works

Extent: E+W+S

(1) Network Rail may, for the purposes of the authorised development, enter on so much of any of the streets specified in Schedule 4 (streets subject to street works) as is within the Order limits and may—
(a) break up or open the street, or any sewer, drain or tunnel under it;
(b) tunnel or bore under the street;
(c) place temporary apparatus in the street;
(d) maintain temporary apparatus in the street and permanent apparatus under the street and, in either case, change its position; and
(e) execute any works required for or incidental to any works referred to in sub-paragraphs (a), (b), (c) and (d).
(2) In this article “apparatus” has the same meaning as in Part 3 of the 1991 Act and “in” as referring to apparatus in the street means under, over, across, along or upon the street.

---
Source: https://www.legislation.gov.uk/uksi/2014/909/article/9 (the official version)