# The Network Rail (Norton Bridge Area Improvements) Order 2014, Paragraph 1

Extent: E+W+S

In this Schedule—
“CEMP” means the Construction Environmental Management Plan to be submitted to and approved by the relevant planning authority, a draft of which is included in Appendix 6, Volume 2 (Folder 2) of the Environmental Statement; and
“Staffordshire Alliance” means the alliance formed by Network Rail with its contractors to progress and implement the works authorised by this Order.

---
Source: https://www.legislation.gov.uk/uksi/2014/909/schedule/2/paragraph/1 (the official version)
Page: https://openlegislation.uk/network-rail-norton-bridge-area-improvements-order-2014/schedule-2/paragraph-1
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.