# The Network Rail (Norton Bridge Area Improvements) Order 2014, Part 2: NATIONAL GRID

Extent: E+W+S

In the County of Staffordshire and the Borough of Stafford
(1)
Number of land shown on land plans
(2)
Purpose for which temporary possession may be taken
(3)
Relevant part of the authorised development
1, 2, 3, 5, 7, 8, 11, 11a, 13, 19, 30, 30a, 37a, 42, 49, 50, 54, 55
Worksites and access to works
Work Nos. 17, 18, 19A and 19B
33, 34, 37, 38
Construction and maintenance of pipe-line
Work No.17
34a (part)
Construction of pipe-line
Work No.17
52, 52a
Worksites and access to works
Work Nos. 17, 18, 19A and 19B
56
Construction of pipe-line
Work Nos. 18, 19A and 19B
57
Worksites and access to works
Work Nos. 18, 19A and 19B
58, 59, 65, 67
Construction of pipe-line
Work Nos. 19A and 19B
61, 66, 77
Worksites and access to works
Work Nos. 19A and 19B
71
Construction of pipe-line
Work No.19A
76, 80, 87, 90, 96
Worksites and access to works
Work Nos. 18, 19A and 19B

---
Source: https://www.legislation.gov.uk/uksi/2014/909/schedule/9/part/2 (the official version)