# The Network Rail (Nuneaton North Chord) Order 2010, Article 10: Access to works

Extent: E+W+S

(1) Network Rail may, for the purposes of the authorised works, and with the approval of the highway authority, such approval not to be unreasonably withheld, form and lay out such means of access, or improve existing means of access, at such locations within the Order limits as Network Rail reasonably requires for the purposes of the authorised works.
(2) If a highway authority fails to notify Network Rail of its decision within 28 days of receiving an application for approval under paragraph (1), that highway authority shall be deemed to have granted approval.

---
Source: https://www.legislation.gov.uk/uksi/2010/1721/article/10 (the official version)
Page: https://openlegislation.uk/network-rail-nuneaton-north-chord-order-2010/article-10
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.

