# The Network Rail (Ordsall Chord) Order 2015, Article 8: Power to deviate

Extent: E+W+S

In constructing or maintaining any of the scheduled works, Network Rail may—
(a) deviate laterally from the lines or situations shown on the works plans to the extent of the limits of deviation for that work; and
(b) deviate vertically from the levels shown on the sections—
(i) to any extent upwards not exceeding 0.5 metres in relation to Works Nos. 1 to 3 and 3 metres in relation to Works Nos. 4 and 5; or
(ii) to any extent downwards as may be found to be necessary or convenient.

---
Source: https://www.legislation.gov.uk/uksi/2015/780/article/8 (the official version)
Page: https://openlegislation.uk/network-rail-ordsall-chord-order-2015/article-8
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.