# The Network Rail (Ordsall Chord) Order 2015, Paragraph 16

Extent: E+W+S

(1) The following provisions of this Part of this Schedule apply for the protection of the lead local flood authority unless otherwise agreed in writing between Network Rail and the lead local flood authority.
(2) In this Part of this Schedule—
“construction” includes execution, placing, altering, replacing, relaying and removal and “construct” and “constructed” are construed accordingly;
“drainage work” means any watercourse and includes any land which provides or is expected to provide flood storage capacity for any ordinary watercourse and any bank, wall, embankment or other structure, or any appliance, constructed or used for land drainage or flood defence;
“lead local flood authority” means in relation to an ordinary watercourse the lead local flood authority concerned within the meaning of section 23 of the Land Drainage Act 1991;
“ordinary watercourse” has the meaning given by the Land Drainage Act 1991;
“plans” includes sections, drawings, specifications and method statements; and
“specified work” means so much of any work or operation authorised by this Order as is in, on, under, over or within 16 metres of a drainage work or is otherwise likely to affect any drainage work.

---
Source: https://www.legislation.gov.uk/uksi/2015/780/schedule/12/paragraph/16 (the official version)
Page: https://openlegislation.uk/network-rail-ordsall-chord-order-2015/schedule-12/paragraph-16
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.