# The Network Rail (Ordsall Chord) Order 2015, Paragraph 51

Extent: E+W+S

(1) Any specified or protective works must, when commenced, be constructed—
(a) without unnecessary delay in accordance with the plans approved or deemed to have been approved or settled in accordance with this Part of this Schedule and with any requirements made under paragraph 47(3) and paragraph 48;
(b) under the supervision (if given) and to the reasonable satisfaction of the engineer;
(c) in such manner as to cause as little detriment as is reasonably practicable; and
(d) in such manner as to cause as little inconvenience as is reasonably practicable to the Trust, its officers and agents and all other persons lawfully using the waterway, except to the extent that temporary obstruction has otherwise been agreed by the Trust.
(2) Nothing in this Order authorises Network Rail to make or maintain any permanent works in or over the waterway which will reduce the dimensions of the waterway or prevent the passage of any vessel which is at the date of this Order able to navigate along the waterway.
(3) Following the completion of the construction of the specified works Network Rail must restore the waterway to a condition no less satisfactory than its condition immediately prior to the commencement of those works.

---
Source: https://www.legislation.gov.uk/uksi/2015/780/schedule/12/paragraph/51 (the official version)
Page: https://openlegislation.uk/network-rail-ordsall-chord-order-2015/schedule-12/paragraph-51
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.