# The Network Rail (Ordsall Chord) Order 2015, Schedule 7: ACCESS TO WORKS

Extent: E+W+S

(1)
Area
(2)
Description of access
Metropolitan district of City of Manchester
Widening of existing access to proposed construction compound off Water Street adjacent to north-eastern side of Prince’s Bridge
Widening of existing access from New Elm Road
Metropolitan district of the City of Salford
Widening of existing access off Water Street to proposed construction compound adjacent to north-eastern side of Castlefield Bridge
Access to be provided to proposed construction compound off Trinity Way to land adjacent to north-western end of Prince’s Bridge
Access to be provided to proposed construction compound off Trinity Way and Irwell Street to land between Stanley Street and Trinity Way
Access to be provided by existing access of East Ordsall Lane
Temporary access required to proposed construction compound from Trinity Way
New access of New Bailey Street
Access to proposed construction site from Chapel Street

---
Source: https://www.legislation.gov.uk/uksi/2015/780/schedule/7 (the official version)
Page: https://openlegislation.uk/network-rail-ordsall-chord-order-2015/schedule-7
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.