# The Network Rail (Oxford Station Phase 2 Improvements (Land Only)) Order 2022, Paragraph 13: Arbitration


Any difference or dispute arising between the undertaker and SGN under this Part of this Schedule must, unless otherwise agreed in writing between the undertaker and SGN, be determined by arbitration in accordance with article 21 (arbitration).

---
Source: https://www.legislation.gov.uk/uksi/2022/871/schedule/5/paragraph/13 (the official version)
Page: https://openlegislation.uk/network-rail-oxford-station-phase-2-improvements-land-only-order-2022/schedule-5/paragraph-13
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.