# The Network Rail (Pont Briwet) (Land Acquisition) Order 2013, Schedule 3: LAND OF WHICH TEMPORARY POSSESSION MAY BE TAKEN


(1)
(2)
(3)
Area
Number of land shown on the land plan
Purpose for which temporary possession may be taken for the authorised works
In the area of Gwynedd Council
1c, 2a, 3a, 5a, 6a, 7a, 7b, 8a, 8b, 9a, 9b, 10a and 11
Working site and access

---