# The Network Rail (Streat Green Underbridge) (Temporary Land Acquisition) Order 2017, Article 9: No double recovery


Compensation is not payable in respect of the same matter both under this Order and under any other enactment, any contract or any rule of law.

---
Source: https://www.legislation.gov.uk/uksi/2017/1302/article/9 (the official version)