The engineer’s approval under paragraph 32 shall not be unreasonably withheld and any question of whether it has been unreasonably withheld shall be settled by arbitration, and in any event if within 56 days after the plans have been furnished to LUL the engineer has not notified his disapproval thereof and the grounds of his disapproval, he shall be deemed to have approved the plans as submitted.

---