# The Network Rail (Waverley Steps) Order 2010, Article 4: Permitted deviation


In constructing or maintaining any scheduled work Network Rail may—
(a) deviate laterally from the lines or situations shown on sheet no. 1 of the Order plans within the limits of deviation for that work shown on that sheet; and
(b) deviate vertically from the levels shown on the Order sections—
(i) in the case of Work No. 1, upwards by a maximum of 0.5 metres;
(ii) in the case of Work No. 3, upwards by a maximum of 1.5 metres; and
(iii) in the case of so much of Work No. 1 as is within plots nos. 1 and 11, and Work No. 3, to any extent downwards.

---
Source: https://www.legislation.gov.uk/ssi/2010/188/article/4 (the official version)
Page: https://openlegislation.uk/network-rail-waverley-steps-order-2010/article-4
Contains public sector information licensed under the Open Government Licence v3.0. Source: legislation.gov.uk, The National Archives.